Project Governance and Cancellation
Let’s consider a potentially common product development scenario as outlined in the following paragraphs.
A product is envisioned which complements an existing product line, but has somewhat limited potential in the form of market size / sales volumes. For various reasons, product management believes the company needs this product offering to complement existing product lines.
Minimal competitive analysis is performed and product critical-to-quality characteristics aren’t determined (ie, no key differentiators ensuring product competitiveness were established). The project is approved in the definition phase-gate review, but it is eventually canceled.
Let’s look at some project governance rules-of-engagement, failure modes and effects. (Our example project followed a phase and gate structure and was canceled during the design phase).

Well-executed project governance, and timely cancellation of projects when necessary, prevents unprofitable projects and misallocation of resources.
It is apparent from the effects listed above, a project can continue to waste time, money and resources if it lingers without cancellation. Reiterating the project governance failure modes:
- Project documentation and pre-reads were not read ahead of gate review
- No key differentiators were apparent which ensured product competitiveness
- Preliminary product cost was too high, but no action was taken to return to the steering committee with updated estimates
- Complaints during gate review about schedule duration, but no additional resources were approved or scope reduced
- Decision was “go” without considering “redirect” to clarify product cost and schedule
- Project did not return to steering committee for re-assessment of the business decision
- Project was not canceled by the steering committee (it was cancelled in one-on-one meetings instead). No post project analysis identified lessons learned.
What would it take to address these failure modes? Let’s consider some countermeasures in the spirit of “blame the process”.
- Clear Roles and Responsibilities (some key roles are as follows):
- Steering Committee Chairperson
- Steering Committee Facilitator
- Opportunity Champion (generally a product manager who stays close to the project execution and monitoring)
- Product Development Core Team Leader / Project Manager (executes and monitors)
- Training:
- All process participants are trained in the governance process
- Training includes what to look for in pre-read materials
- Project Constraint Recognition and Alleviation:
- There are only three levers: scope, resources and schedule
- Rules of Engagement
- For example, project returns to the steering committee if the gate schedule slips by more than 4 weeks
- Tools and Templates
- Standardized deliverables and steering committee pre-reads
- Post project analysis template
One can see it is a fair amount of work-effort to put a governance process in place, something generally done by a project management office (PMO).
However, the alternative is likely project quality ‘escapes’ and delayed cancellation, potentially costing a company millions. Any company with multiple product development projects should consider project governance as a key business decision-making process and continuously improve that process accordingly.
Categories
- Agile (3)
- Change Management (7)
- Design for Six Sigma (7)
- Ideation (1)
- Lean Manufacturing (4)
- Lean Product Development (11)
- Maximizing Customer Value (7)
- Portfolio Analysis (2)
- Product Lifecycle Process (8)
- Project Governance (2)
- Project Management (19)
- Requirements Management (10)
- Roles and Responsibilities (6)
- Six Sigma (5)
- Supply Chain (2)
- Systems Integration (2)
- Uncategorized (4)
- Value Stream Management (5)
- Verification and Validation (6)